NEPS can provide personnel experienced in the development/review of the environmental and performance test and demonstration protocols.
Facility, contracts typically require initial test protocol delivery 5 months prior to contract testing. Protocol development typically requires 2-3 months prior to initial issue.
Protocol review typically requires 2+ months depending on the attention paid to the review and resolution of the activities and methods associated with the protocol.
Some demonstrations can be planned to or will occur during the commissioning activities. Owner/Operator staff witness and well documentation of these occurrences can eliminate the need for re-demonstration and thus reduce the test period. This evolution to be addressed in the protocols.